Following four weeks of work done at Plant Kariega to upgrade its production facilities, Volkswagen Group Africa has embarked on the next phase of its preparations for the third model it will build from 2027.
Plans to add this model, an A0 SUV Entry vehicle, to the production line in Kariega alongside the Polo and Polo Vivo were announced at the VW Indaba media event in February this year. At this point, about 60% of the preparation work in Production had already been completed during the December 2024 shutdown.
From 14 April to 12 May, the plant halted production to complete the remaining 40% of the required installations and upgrades in the Body Shop, Paint Shop, and Final Assembly areas. This work included finalising all installations completed in the Body Shop, station modifications and the programming of robots in the Paint Shop, and modifying conveyors in Final Assembly, among other tasks.
With this work completed and production returning to normal, the A0 SUV Entry project is now in its commissioning phase. This entails a systematic process of bringing the new equipment online and performing necessary checks to ensure these is functioning optimally. This is being done over weekends in order to prevent any disruption to Plant Kariega’s production over three shifts.
The A0 SUV Entry project is an exciting one for Plant Kariega, as VWGA is working closely with colleagues in Volkswagen do Brasil to develop, build and launch this model.
“We are happy to be back to normal production, with the knowledge that we are one step closer to our future of building three models in our plant,” said VWGA Production Director, Ulrich Schwabe. “I would like to thank every employee who has played a part in the process of preparing for this future icon in our Volkswagen line-up, and I look forward to working with these colleagues, as well as our Brazilian counterparts, as we continue on this journey.”